Theatres building at Poole Hospital handed over

Poole Theatres handover

The AD-designed theatres block at Poole Hospital was handed over to the Trust ahead of schedule last week. The building provides eight state-of-the-art theatres, arranged over two floors with direct access to the Hospital’s existing theatres department. In the open-plan barn theatre four operating tables, each with dedicated ultra-clean ventilation, offer the Trust flexibility and increased throughput for elective procedures.

The second phase of the redevelopment, which will re-provide admission, 1st and 2nd Stage recovery spaces in the Hospital’s existing Block A is due to commence shortly.

The project was a great team effort from all involved, including the client University Hospitals Dorset NHS Foundation Trust, contractor IHP (VINCI Construction UK Ltd & Sir Robert McAlpine), MEP engineer Troup Bywaters + Anders, structural engineer Curtins, planning consultant Savills and UVC supplier Howorth Air Tech.

Share this page: